Steel stud makers scheduled 70 price increases in 2026, and January is already on the calendar
Nov. 9, 2026
Nine steel stud and track makers have 70 price increases with effective dates in 2026, the last on December 1. Sixty-five have already taken effect. We counted each one only after checking it against the maker's posted notice. Three of them have already announced a round for January 4, 2027.
How often each maker raised prices
| Maker | Increases effective in 2026 | Already announced for Jan 2027 |
|---|---|---|
| CEMCO | 12 | none yet |
| ClarkDietrich | 10 | Jan 4 |
| MarinoWare | 10 | Jan 4 |
| MBA Building Supplies | 10 | Jan 4 |
| Telling Industries | 8 | none yet |
| Mill Steel Framing | 7 | none yet |
| Ram Steel Framing | 5 | none yet |
| EB Metal / Super Stud | 4 | none yet |
| Steel Construction Systems | 4 | none yet |
These are minimum counts. We only see letters that distributors post publicly. A maker that skipped a month in our chart may have raised prices anyway.
CEMCO's own letter backs up our count. Its October 23 notice for a November 30 increase says: "This will be our 12th announced increase in 2026, an unprecedented development in our 52-year history." Our database has 12 CEMCO effective dates in 2026, which matches (CEMCO letter).
Eight increases are still ahead
As of November 9, eight announced increases have not taken effect yet.
- November 30: CEMCO.
- December 1: ClarkDietrich, MarinoWare, MBA Building Supplies and Telling Industries.
- January 4, 2027: ClarkDietrich, MarinoWare and MBA Building Supplies.
ClarkDietrich and MBA announced their December and January rounds in a single letter in early November. ClarkDietrich's November 2 letter says the two increases "respond to continued domestic steel mill price increases and surcharges passed in the coming months" (ClarkDietrich letter). MarinoWare's January letter sets a floor of 10% and says it comes "in addition to the previously announced November and December 2026 increases" (MarinoWare letter). The full list is on our upcoming price increases page and the drywall and interiors page.
Most letters don't say how much
Only 16 of the 73 letters put a number on the base increase. Thirteen of those say "a minimum of 10%". The other three are Ram Steel Framing's 15% in January, "up to 10%" in March and 10% in May. The other 57 letters say prices go up and point buyers to new price sheets.
So a median percentage would mislead here, and we don't report one. The count of rounds is the more reliable signal.
The floors still add up. MarinoWare put a minimum of 10% on seven of its 2026 rounds. If all seven applied in full to the same list price, the floors alone compound to about 95% (1.1 to the 7th power is 1.949). That is list-price arithmetic. Contractors' net prices depend on discounts, project quotes and distributor terms, and we don't see those.
How much notice buyers got
We matched 69 letters to the date printed on the letter. The median gap between that date and the effective date was 33 days. The shortest was 26 days and the longest was 63. The long gaps are the January 4 rounds. ClarkDietrich and MBA announced those rounds on November 2 and 3, in the same letter as a December increase. MarinoWare's December letter is dated October 30.
In practice, a stud quote priced today is likely to cross at least one new price sheet before the material ships. Several letters say so directly. ClarkDietrich's October and November letters say that "invoice pricing is determined at the time of shipment" and that existing quotes are honored under its job quote policy. MarinoWare's January letter adds that it is "evaluating the duration of our current quote policy."
What the makers say is driving it
These are the makers' explanations in their own letters. They are not our conclusions.
- CEMCO, October 23: "Domestic steel mills have been running behind schedule due to supply constraints caused by the limited availability of imported steel in the United States. As a result, mills continue to raise prices month-over-month."
- ClarkDietrich, October 2 (for November 1): the increase "responds to the latest round of domestic steel mill price increases and surcharges for November shipments, as well as the ongoing escalation of steel input & energy costs throughout 2026" (ClarkDietrich letter).
- Telling Industries, November 2: "Domestic Steel Mill costs have continued to climb as we near the end of 2026. Additionally, transportation and fuel costs have remained at increased levels" (Telling letter).
- MarinoWare, October 30: "Due to continuing price increases from domestic steel producers" (MarinoWare letter).
Public steel data points the same way. The Bureau of Labor Statistics producer price index for steel mill products rose from 315.369 in January 2026 to 388.580 in September, up 23.2%. June through September are still preliminary (BLS series WPU1017). These figures are context. They line up with what the makers wrote, but they don't prove the size of any one stud increase.
What this means for estimators
- Check the effective date and the ship date, not the bid date. Half the letters gave 33 days of notice or less.
- Ask your distributor which price sheet a quote is built on, and whether the job is registered under the maker's job quote policy.
- Expect more rounds. Four makers have December dates, three have January dates, and none of the letters we read says the run is over.
Method and limits
- Data: the PriceLetter letters table, exported read-only on November 9, 2026. We counted active, non-duplicate increase letters from nine steel stud and track makers with effective dates from January 1, 2026 to January 4, 2027.
- We checked every increase in the count against the maker's letter as a distributor posted it. For two (ClarkDietrich March 2 and MBA April 6) we could only read Negwer Materials' dated summary of the letter. We extracted text from PDFs, ran OCR on image files and matched the maker's name and effective date. The effective date is the date the price applies. It is not the letter date or the date PriceLetter found the letter.
- We merged three MBA Building Supplies listings into one maker and counted two letters from the same maker less than 10 days apart as one increase.
- We left out four records. One was a Hunter Panels letter filed under Telling Industries. One was a ClarkDietrich letter about Strait-Flex and Vinyl Corp products, not studs. One was a second copy of ClarkDietrich's November 1 letter under a November 2 date. One was an EB Metal listing from Universal Supply with no letter we could open.
- On November 9 we fixed four database rows found while drafting: the Hunter Panels letter misfiled under Telling (now marked duplicate of the Hunter Panels letter), two Steel Construction Systems effective dates (May 11 and October 5), and a second ClarkDietrich November 1 copy. The counts above use those corrected dates. MBA remains split across three brand pages until a redirect release; this post still counts MBA as one maker.
- Percentages are list-price changes as the makers announced them. They are not net contractor costs.