Home › Analysis › Steel stud increases

Steel stud makers scheduled 70 price increases in 2026, and January is already on the calendar

Nov. 9, 2026

Nine steel stud and track makers have 70 price increases with effective dates in 2026, the last on December 1. Sixty-five have already taken effect. We counted each one only after checking it against the maker's posted notice. Three of them have already announced a round for January 4, 2027.

Steel stud and track makers: price increases by effective date, Jan 2026 to Jan 2027
Steel stud and track makers: price increases by effective date, Jan 2026 to Jan 2027

How often each maker raised prices

MakerIncreases effective in 2026Already announced for Jan 2027
CEMCO12none yet
ClarkDietrich10Jan 4
MarinoWare10Jan 4
MBA Building Supplies10Jan 4
Telling Industries8none yet
Mill Steel Framing7none yet
Ram Steel Framing5none yet
EB Metal / Super Stud4none yet
Steel Construction Systems4none yet

These are minimum counts. We only see letters that distributors post publicly. A maker that skipped a month in our chart may have raised prices anyway.

CEMCO's own letter backs up our count. Its October 23 notice for a November 30 increase says: "This will be our 12th announced increase in 2026, an unprecedented development in our 52-year history." Our database has 12 CEMCO effective dates in 2026, which matches (CEMCO letter).

Eight increases are still ahead

As of November 9, eight announced increases have not taken effect yet.

ClarkDietrich and MBA announced their December and January rounds in a single letter in early November. ClarkDietrich's November 2 letter says the two increases "respond to continued domestic steel mill price increases and surcharges passed in the coming months" (ClarkDietrich letter). MarinoWare's January letter sets a floor of 10% and says it comes "in addition to the previously announced November and December 2026 increases" (MarinoWare letter). The full list is on our upcoming price increases page and the drywall and interiors page.

Most letters don't say how much

Only 16 of the 73 letters put a number on the base increase. Thirteen of those say "a minimum of 10%". The other three are Ram Steel Framing's 15% in January, "up to 10%" in March and 10% in May. The other 57 letters say prices go up and point buyers to new price sheets.

So a median percentage would mislead here, and we don't report one. The count of rounds is the more reliable signal.

The floors still add up. MarinoWare put a minimum of 10% on seven of its 2026 rounds. If all seven applied in full to the same list price, the floors alone compound to about 95% (1.1 to the 7th power is 1.949). That is list-price arithmetic. Contractors' net prices depend on discounts, project quotes and distributor terms, and we don't see those.

How much notice buyers got

We matched 69 letters to the date printed on the letter. The median gap between that date and the effective date was 33 days. The shortest was 26 days and the longest was 63. The long gaps are the January 4 rounds. ClarkDietrich and MBA announced those rounds on November 2 and 3, in the same letter as a December increase. MarinoWare's December letter is dated October 30.

In practice, a stud quote priced today is likely to cross at least one new price sheet before the material ships. Several letters say so directly. ClarkDietrich's October and November letters say that "invoice pricing is determined at the time of shipment" and that existing quotes are honored under its job quote policy. MarinoWare's January letter adds that it is "evaluating the duration of our current quote policy."

What the makers say is driving it

These are the makers' explanations in their own letters. They are not our conclusions.

Public steel data points the same way. The Bureau of Labor Statistics producer price index for steel mill products rose from 315.369 in January 2026 to 388.580 in September, up 23.2%. June through September are still preliminary (BLS series WPU1017). These figures are context. They line up with what the makers wrote, but they don't prove the size of any one stud increase.

What this means for estimators

Method and limits